PrestoMobile Implementation Schedule (~ 8-10 Weeks)

PrestoSports is thrilled about our partnership and are excited to get the project process started.

Client Personnel: To support PrestoSport’s collaborative Implementation, PrestoSports expects that Client’s personnel are identified and made available to collaborate with their PrestoSports counterparts throughout the Implementation. Below is a breakdown of the key roles and responsibilities of each role during the Implementation.


Phase 1 - Kickoff (~ 1 Week)

The Project Kickoff Call serves as the project kickoff between the client team and the PrestoSports team. During this time we will make introductions for all team members on the call and will have a high-level overview of the entire project plan.

Implementation

Action

Responsible Party

PrestoSports

Client

Onboarding Email

 

Project Kickoff Call

Submit PrestoMobile Starter Kit

Provide logos and images for app assets

Apple Developer Account Membership Set Up*

*This action is only required for Standalone Applications.

Phase 2 - Design & Build (~ 4 to 6 Weeks)

Set up of mobile application based on the submitted starter kit and media collateral (i.e. home screen design, prep files, marketing materials, module selection, and app build + submission).

Implementation

Action

Responsible Party

PrestoSports

Client

Home Screen Design Approval

Creation of Prep Files & Marketing Materials

 

App Build*

Beta App & App Store Submission**

*For Standalone Apps only, this action cannot begin until Apple Developer Account access has been granted.
**This action is only required for Standalone Applications.

Phase 3 - App Test & Training (~ 1 Week)

On the application is built the Implementation Team-member will share testing details with the client team. A dashboard training meeting will be scheduled so that the client team can become more familiar with all of the PrestoMobile features and settings.

PrestoRaise

Action

Responsible Party

PrestoSports

Client

App Testing Instructions Shared

Register on app & share username w/ PrestoSports

 

Admin Dashboard Access Granted

~45 minute Dashboard Training Session


Phase 4 - Content Loading (~ 1 Week)

After the dashboard training session the client team will be fully equipped with all PrestoMobile knowledge and features to begin entering content onto application preparing for launch.

PrestoRaise

Action

Responsible Party

PrestoSports

Client

PrestoWeb to PrestoMobile Integration*

iCal Event Calendar Import**

Manual Event Entry

Reward Set Up

*This action is available to client’s who have an active PrestoSports website.
**For an iCal event calendar import to be completed the client team must send a request to the Implementation Team-member along with additional details needed to complete this action. The standard timeline for iCal imports is 5-10 business days.

Phase 5 - Launch (~ 1 Week)

Once the client team is ready to launch the PrestoMobile application to their fanbase the Implementation Team member should be notified as there are a few additional actions that need to take place.

PrestoRaise

Action

Responsible Party

PrestoSports

Client

Client Notification of Launch Date

Sharing of Marketing Material Files

Standalone App Release (iOS & Android)*

Confirmation of Live App

Sharing of Public Download Links

Launch Platform to Fanbase

*This action is only required for Standalone Applications. The standard timeline for the Apple App Store and the Google Play Store to release a new app to live is 2-4 business days.

With the Implementation Process being complete at this point, the client team can use our contact our Support team using this form for additional support if needed.